# ⚠️ Risk Management in Software Projects ## 1. 🎯 Learning Objectives - Identify software project risks - Create a risk matrix (probability × impact) - Plan risk mitigation and contingency ## 2.

⚠️ Risk Management in Software Projects
1. 🎯 Learning Objectives
- Identify software project risks
- Create a risk matrix (probability × impact)
- Plan risk mitigation and contingency
2. 📖 Core Content
3.1 Risk Categories
Technical: Technology changes, complexity, performance issues Project: Schedule, budget, resource constraints Organizational: Priority changes, team turnover External: Market shifts, regulatory changes
3.2 Risk Matrix
| Probability\Impact | Low | Medium | High |
|---|---|---|---|
| High | Monitor | Mitigate | Avoid |
| Medium | Accept | Monitor | Mitigate |
| Low | Accept | Accept | Monitor |
3.3 Mitigation Strategies
- Avoid: Change approach to eliminate risk
- Mitigate: Reduce probability or impact
- Transfer: Insurance, outsourcing
- Accept: Acknowledge and budget for consequences Join Discord PreviousTesting in SDLCNextCI/CD & DevOps